Update of Satellite Facility at Sotnikum

As of September 30th, the building for the satellite project at Sotnikum is 80% complete. Due to some cost savings, the building has been extended to 17 x 17 meters and has a covered waiting area in front. In addition, the water tank for the entire Sotnikum hospital has been refurbished and a donated water purification system will be installed in December which will benefit the entire facility.
Overall, the project is a little ahead of schedule. Currently, the supplies and equipment for the facility are being purchased and training for new staff will begin in the next few months ahead. A combination of expatriate and Khmer Physician staffing will ensure both enough quantity and quality of staffing to make the venture successful.